Moving South
31 May 2017

Moving South

Construction is finishing up on the north end of town in the next day or two. Our crews have now begun work in the area south and west of Rush Creek. We have fiber up to the new school; splicers are now working there. 


- 917 homes and businesses will be addressed with this fiber build

- Construction will take place throughout the summer of 2017
- Most of May will be spent on the north end of town
- June will be spent working near the middle of the town, those locations fed by the central office
- Work in July will include the area south of the school, east of Rush Creek
- August will be spent working on South Rushford Village

- Splicing will follow construction and will continue through the end of the year