11 December 2017

Work Continues

Installations continue on the north end of town, hooking up roughly 20-25 homes per week. Businesses also located on the north end of town have also been hooked up. We will continue moving towards the heart of the city as progress continues installing services to our customers.


- 917 homes and businesses will be addressed with this fiber build

- Construction will take place throughout the summer of 2017
- Most of May will be spent on the north end of town
- June will be spent working near the middle of the town, those locations fed by the central office
- Work in July will include the area south of the school, east of Rush Creek
- August will be spent working on South Rushford Village

- Splicing will follow construction and will continue through the end of the year