Construction Phase Complete
20 July 2017

Construction Phase Complete

The construction phase of the fiber build in Rushford is now complete.  The next step in the process is splicing, which will continue through the end of the year. The overall fiber project looks to be on track for a completion date of March 2018.

THE PLAN:

- 917 homes and businesses will be addressed with this fiber build

- Construction will take place throughout the summer of 2017
- Most of May will be spent on the north end of town
- June will be spent working near the middle of the town, those locations fed by the central office
- Work in July will include the area south of the school, east of Rush Creek
- August will be spent working on South Rushford Village

- Splicing will follow construction and will continue through the end of the year